- Fiat Construction Services;
- SMA Builder;
- KVC Construction;
- M.M.A. Achiever Construction & Development Corp.;
- Ren Ren Trading & Construction Services;
- Excelsius Engineering Services; and
- Golden Gate Construction.
- 77.80 rating for the “Road Upgrading (Gravel to Paved) of San Isidro - Daja Road K1018+(-497)” in Region VIII worth P45.3 million;
- 78.40 rating for the “Rd. Upgrading (Gravel to Paved) of Tabango-Catmon-La Fortuna-Manlawaan-Gimarco Rd., Km.1040+297- Km.1042+307” in Region VIII worth P44 million;
- 76.30 rating for the “Rd. Upgrading (Gravel to Paved) of Tabango-La Fortuna-Manlawaan-Gimarco Rd. Km.1040+297-Km.1042+307” in Region VIII worth P44 million;
- Marawi Shelter-Package 3, Supply and Installation of Transitory Shelter in Marawi City under Modified Design and Build Contract Package 3 worth P41.7 million; and
- Marawi Shelter-Package 2, Supply and Installation of Transitory Shelter in Marawi City under Modified Design and Build Contract Package 2, P49.4 million.
- A contract worth P42,072,597.80 awarded to Golden Gate to build 265 shelter units originally, but which had been revised to 204 units, all supposedly completed. The contract was bidded out on Sept. 29, 2017, awarded on Oct. 3, but the notice to proceed was issued only on Nov. 29 last year. A total of 198 units in the project site are now occupied, from a target of 197 units for occupancy.
- A contract worth P49,361,405.85 awarded to Excelsius Engineering to construct an original 309 shelter units but which had been revised to 292 units, all “completed.” The contract was bidded out on Oct. 3, 2017, awarded on Oct. 18, and the notice to proceed issued on Nov. 21. NHA said 93 of the 102 units ready for occupancy are now occupied.
- A second contract for Excelsius Engineering worth P41,693,614.65 for the construction of 261 shelter units originally, but revised to only 219 units. The bidding was conducted also on Oct. 3, 2017, the notice of award issued on Oct. 18, and the notice to proceed, on Nov. 29, 2017. NHA said that 205 of the target 215 units are now actually occupied.
- The “City Government of Marawi” was listed by NHA as the “contractor” of a fourth ongoing project worth P53.6 million. NHA said that this involved the construction of 335 shelter units, all “completed.” The fund for the project, the agency said, “was transferred to Marawi City LGU.” Only 188 of the 248 target units in the project site are now occupied but NHA said that the “schedule for the occupancy of the remaining units is set to (go) full blast after Ramadan.” The NHA report does not show when and to which contractor the Marawi City government bidded out and awarded this contract.